Thursday, October 28, 2010

Aluminum siding & windows

I've been remiss in posting once again, but progress has been good since framing completed. As you can see from this first picture, most of the white aluminum panel siding (done in a rainscreen application over Vaproshield) is on. The wrapped siding under the cantilever has to wait until insulation has been applied. The lower volume will have stucco, and the first stage of wrapping the sides in two layers of tar paper is complete.



The windows in the lower volume are all black Milgard aluminum. I love the graphic pop of the black windows against the white siding.



We decided to delay ordering the windows until framing was complete, because most of our windows are floor-to-ceiling and we wanted to make sure the windows fit the rough openings perfectly. Unfortunately, this choice is causing about a month of delay, and the wood Lindal windows have not arrived, yet.

The master bedroom window was too large to be built as one unit, so it was split into three pieces separated by 2x6's that will later be encased in black metal to make it look more like one.



The TPO roofing is also in, and can be seen on the 2nd floor deck, here. Sleepers and cedar decking will go on top.



Electrical and plumbing rough-ins are also mostly complete. Radiant heating on the first and third floors are embedded in concrete, but the second floor will be heated by tubes running in the joists, with heat transfer aided by aluminum ultra-fins attached to the tubes.



The windows under the floating stair are in, and look super cool; the stair treads themselves are temporary.



Finally, the front door and side windows are installed; the door is 8-ft tall and runs floor to ceiling. We plan to paint it bright red.




The wood Lindal windows are arriving today, but the Lindal sliding doors will take another two weeks. So the plan is to bubble in the remaining openings and turn on the heat to completely dry the wood out; after that, we can install insulation and start drywall, which can take two weeks. Then the more fun finishes, such as tile and flooring and cabinets, can start!

One slightly annoying issue is our gas line. We thought gas was stubbed to the property, but Puget Sound Energy didn't like the stub, for some reason. At first, they told me that it would cost $3k-$4k to run gas from the street. Then, it went down to $2k plus $0.17 per therm for the next 5 years, which should add up to less. After that, our superintendent at Logan's Hammer called them, and the up-front cost went down to $848! So, now we have gas and an unsightly patch in the road, which they say will eventually be replaced. But fortunately the cost wasn't so bad.